Project

Kestrel Row
ground floor

A tired ground floor opened into one room, with a new kitchen, a utility and a living space finished in eleven weeks.

The brief

One room instead of four

The owners cooked in a galley at the back of the house and never used the front room. We took out two partitions, moved the services and turned the whole floor into one space that gets light from both ends.

LocationAlder Park
ScopeKitchen, utility, living room
On site11 weeks
FinishedMarch 2026
The ground floor after renovation
The ground floor before renovation
Before After

On the day we left

Room by room

Photographs taken the morning after the final clean, before any of the owners' furniture went back in.

Walnut dining room at duskThe living room after handbackUtility room in sage cabinetry
New kitchen with a stone islandCovered terrace loungeCharcoal kitchen with slim pendants
Open plan floor toward the studyBedroom with oak joineryBathroom with a freestanding tub

How this one ran

Eleven weeks, three stages

The same three stages every project gets, with the dates this one actually hit.

01

Weeks 1 to 2

Survey, structural check on the two partitions, fixed price signed and the cabinetry ordered.

02

Weeks 3 to 9

Partitions out, steel in, new drainage and circuits, plaster, floor, then the kitchen fit.

03

Weeks 10 to 11

Decoration, snag list cleared, appliances tested and a full clean before handback.

Start a project

Tell us about the room you want back

Send the basics and we will come back with the next steps, a likely start window and a price range.

Demonstration form. Nothing is sent and no details are stored.

Thanks, that is with us.
This is a demo theme, so nothing was actually sent. On a live site the studio would reply within one working day.
Charcoal kitchen with slim pendant lights and three stools at an oak counter